2013
07.012013

Architectural competition

Timing: 2013 / 2014

2014
18.122014

Architects be baumschlager eberle submit the winning project

Timing: end of 2014

24.122014

Strip-out works

July 2014 - December 2015

2015
25.112015

Permit structural works Rue Royale 20

2016
08.012016

Environmental and urban planning certification

12.012016

Demolition en site permit classification III

18.012016

Demolition starts

Timing demolition works: 2016 / 2017

01.052016

demolition towers

May - October 2016

01.092016

demolition base

September 2016 - March 2017

2017
15.062017

Construction starts

Timing contruction works: 2017 / 2021

2021
15.122021

Building ready for occupation

Timing: end 2021